S.No Payment Due Percentage (%) Other Charges
1. On Booking* As Applicable*  
2. On or Before 2months from the date of Application 20% of BSP – Booking Amount*  
3. On or Before 4 months from the date of Application 15% IDC
4. On commencement of excavation 15% Car Park
5. On completion of ground floor roof slab 10%  
6. On completion of 1st floor roof slab 10%  
7. On completion of the top floor Roof Slab 10% ESSC
8. On completion of internal plaster &flooring within the apartment 10% Social Club Membership + Maintenance Advance + IFMD + Lease Rent
9. On offer of Possession 10%
  Total 100%  
 
     
  B. Down Payment Plan  
 
S.No Payment Due Percentage (%) Other Charges
1. On Booking* As Applicable*  
2. On or before 1 month from date of Application 95% of BSP – Booking Amount* IDC +Car Park+ ESSC
3. On offer of possession 5% Social club membership + Maintenance Advance +IFMD + Car Park + ESSC + Lease Rent
  Total 100%  
 
  Down payment discount: Upto12% on BSP based on stage of construction.  
  C. Construction Linked Plan (for G+6 floors)  
 
S.No Payment Due Percentage (%) Other Charges
1. On Booking* As Applicable*  
2. On or Before 2 months from the date of Application 20% of BSP – Booking Amount*  
3. On or Before 4 months from the date of Application 10% IDC
4. On commencement of excavation 10% Car Park
5. On completion of upper basement slab 10%  
6. On completion of 2nd floor roof slab 10%  
7. On completion of 4th floor roof slab 10% ESSC
8. On completion of the top floor Roof Slab 10%  
9. On completion of internal plaster &flooring within the apartment 10%  
10. On offer of Possession 10% Social Club Membership + Advance + IFMD + Lease Rent
  Total 100%  
 
  Note:
• *Booking Amount
• 1/2 BHK @ Rs. 2 Lacs, 3 BHK (all types) @ Rs. 3 Lacs , 4 BHK (all types) @ Rs. 4 Lacs
• Installments under S. No. 4 - 10 may run concurrently with those under S. No. 1 - 3 based on the physical progress of Work at site.
• The demand letter for Installments at S. No. 4 to 10 shall be sent in advance providing for payment period of up to 15 days.
 
     