| 1. |
On Booking |
As Applicable** |
|
| 2. |
On or before 2 months from the date of Application |
20% of BSP (less Booking Amount**) |
|
| 3. |
On or Before 4 months from the date of Application |
10% of BSP |
|
| 4. |
On commencement of excavation |
10% of BSP |
|
| 5. |
On laying of upper basement slab |
10% of BSP |
|
| 6. |
On laying of 3rd floor roof slab |
7% of BSP |
Car parking |
| 7. |
On laying of 7th floor roof slab |
7% of BSP |
IDC |
| 8. |
On laying of 11th floor roof slab |
6% of BSP |
EDC |
| 9. |
On laying of 15th floor roof slab |
5% of BSP |
PLC |
| 10. |
On laying of 19th floor roof slab |
5% of BSP |
|
| 11. |
On laying of 22nd floor roof slab |
5% of BSP |
ESSC |
| 12. |
On laying of top floor roof slab |
5% of BSP |
|
| 13. |
On completion of internal plaster & flooring within the apartment |
5% of BSP |
|
| 14. |
On offer of Possession |
5% of BSP |
Social club membership + Maintenance advance + One time Lease Rent + IFMD |
| |
Total |
100% |
|